To estimate DualSun installation costs our tool MyDualSun of energy and economic simulation was developed and based on reliable assumptions of exposure time.
To estimate the time required for a DualSun installation watch the installation instruction video tutorial.
For a house with 4 or 6 hybrid DualSun SPRING panels
Here is some information gathered from our installers regarding the installation of DualSun panels.
- Human resources: 3 people
- Plumber work in the machine room and bring the hydraulic pipes to the roof.
- Fitters work on the roof to set up the fastening system and install the solar panels.
Team |
Day 1 |
Day 2 |
Machine Room = Plumber |
x |
x |
Roof = fitters |
x |
x |
Example of planning
Day 1
- The fitters arrive on site, install scaffolding and safety equipment. They climb on the roof, install the fastening system.
- The plumber installs the solar tank and the solar station. He runs the hydraulic lines from the technical room to the roof and back together with the installers.
Day 2
- The fitters install the panels, proceed to the electrical and hydraulic connections of the panels.
- The plumber positions and connects the DualSun solar station to the solar tank and makes the hydraulic connections of the domestic water to the new tank.
- He then performs a water pressure test during which he and the fitters go around the connections to check the tightness of the circuit.
- At the end of the day or the next morning, the hydraulic commissioning of the system can take place.